Construction of Estonian Cell wastewater treatment plant (Estonian Cell AS)

2013
  • Electrical installation works
  • Heavy current works
  • Automation works
  • Delivery of 690/400 V, 400 kVA, IP31 low voltage dry-type transformer

Construction of Tamme water treatment plant (Matsalu Veevärk AS)

2013
  • Designing electrical and automation parts
  • Electrical installation works
  • Writing and setting up the logic program for process automation of the water treatment plant

Construction of Teaduse water treatment plant (Saku Maja AS)

2013
  • Designing electrical and automation parts
  • Electrical installation works
  • Writing and setting up the logic program for process automation of the water treatment plant

Construction of Kannikese water treatment plant (Saku Maja AS)

2013
  • Designing electrical and automation parts
  • Electrical installation works
  • Writing and setting up the logic program for process automation of the water treatment plant

Construction of Nurme water treatment plant (Saku Maja AS)

2013
  • Designing electrical and automation parts
  • Electrical installation works
  • Writing and setting up the logic program for process automation of the water treatment plant

Construction of Lehola wastewater treatment plant (Lahevesi AS)

2013
  • Designing electrical and automation parts
  • Automation works, including writing and setting up a station's process automation program

Construction of Kurvi water treatment plant (Elveso AS)

2012
  • Designing
  • Heavy current works
  • Electrical installation works
  • Weak current works
  • Automation works, including writing and setting up a process automation program

Construction of Sarruse reinforcement pressure booster pumping station (Elveso AS)

2012
  • Designing
  • Heavy current works
  • Electrical installation works
  • Weak current works
  • Automation works, including writing and setting up a process automation program