Construction of Rakvere 5.6 MW ORC combined heat and power cogeneration plant fuelled by woodchips, stage I (Adven Eesti AS)

2013
  • Delivery and installation of electrical and automation equipment
  • Medium voltage works 10.5 kV
  • Heavy current works
  • Automation works
  • Electrical installation works
  • Writing and setting up the logic program for process automation of the cogeneration plant, including creating of remote monitoring (SCADA)

Construction of Paide 2.1 MW combined heat and power cogeneration plant fuelled by woodchips (Eesti Energia AS)

2013
  • Medium voltage works, at rated voltage 10.5 kV
  • Electrical installation works
  • Automation works
  • Building the fire detection and alarm system (ATS)

Construction of Rakvere 5.6 MW ORC combined heat and power cogeneration plant fuelled by woodchips, stage II (Adven Eesti AS)

2014
  • Delivery and installation of two 2x325 kVar, cos(fi)=0.99 capacitor sets
  • Delivery and installation of 690 V, 2500 A busbar trunking system
  • Electrical installation works
  • Installation works of automation